From: Makarius <makarius@sketis.net>
Reminder: the release plan is here
https://sketis.net/2025/plan-for-isabelle2026-october-2026
I have shifted the start with RC1 5 days further ahead: 19-Sep-2026, and the
critical fork-point 2 weeks later as before, 03-Oct-2026. Thus we will be
mostly in sync with the AFP fork-point.
So there are now < 2 weeks left to get everything ready for RC1. Then there
will be precisely 2 weeks to react on feedback by users, on the regular
isabelle-dev repository.
After 03-Oct-2026, any further changes that are really relevant for the
release need to be sent to me via e-mail (from "hg export" or "hg bundle").
Makarius